Hampton West is ‘substantially complete’
Subhead
Village board approves final bill for infrastructure
The Hampton Village Board has signed off on the completion of the utility, street and other infrastructure work for the new Hampton West Subdivision. The board of trustees took action at its November meeting on Monday night to approve the final application for payment from Mid Nebraska Land Developers including a change order and to issue the certificate of substantial completion on the project...